Ilisu Dam

The Ilisu Dam was the first ever project to have export credit guarantees from European governments withdrawn after the guarantees had already been agreed. ECA Watch members campaigned hard to make this happen.


Ilisu dam - history and current situation 

In 2008 the German, Austrian and Swiss governments pulled out of the Ilisu Dam project in Turkey, reflecting the serious social, cultural and environmental risks the project posed. This was the first time any European government suspended an agreed export credit guarantee. Turkey however is still pushing ahead with construction of the dam.


2001/2200720082009
Turkey's first attempt at financing the dam failed due to environmental & social concernsAustria, Germany, Switzerland all agree to provide export credit guarantees for Ilisu damExperts find resettlement program for Ilisu dam violates conditions-credit guarantees suspendedGermany, Austriaand Switzerland officially withdraw export credit guarantees

The Ilisu dam

Turkey’s Ilisu Dam project was planned for the Tigris river in the 1950s, as part of the much larger Greater Southeast Anatolian Project (GAP). As Turkey’s largest dam project, Ilisu would have displaced approximately 65,000 people, mostly Kurdish; destroyed 400 km of river ecosystems; and submerge the 12,000 year old town of Hasaneyf.

Ilisu was envisaged primarily as a hydropower dam, although flood defence was also cited in the rationale for its construction.

How are ECAs involved

Turkey’s first attempt to finance the Ilisu dam faltered in 2001/2 as, under pressure from intense campaigning on environmental and social concerns,  almost all the banks involved walked away from the project.  The government made another attempt to finance the dam in 2004/5, when a consortium of contractors applied for export credit guarantees in Austria, Germany and Switzerland. These ECAs offered their support on condition that certain international standards were met.

In 2005 Austria, Germany, Switzerland and Turkey negotiated 153 conditions for ECA financing of the Ilisu dam. These included standards for resettlement, environmental protection, cultural heritage, and transboundary impacts. The 153 conditions were not made public until after the export credit guarantees had been approved. When NGOs and international experts were able to see the conditions, many argued that they were insufficient to bring the Ilisu project in line with international law or World Bank standards.

The ECAs signed financing agreements in 2007. According to these agreements, if the 153 conditions were not met, a three step exit procedure was envisaged:

  • If ECA-appointed experts confirmed violation of the conditions, Turkey would be issued with an Environmental Failure Notice with a 60 period to fix the problems
  • If there was no substantial progress made in 60 days, the export credit contracts would be suspended for 180 days
  • If there was still no evidence of improvement within 180 days or no certainty that the conditions would be met in the future, the contracts would be cancelled.

Standards are not met

In 2007 contractors began expropriating villages closest to the Ilisu construction site. The Berne Declaration revealed major problems with the exercise, with very poor compensation for the displaced villagers and a lack of resettlement land provided. Experts commissioned by the ECAs to monitor the implementation of the 153 conditions confirmed these problems.

This failure to adhere to the conditions led Austria, Germany, and Switzerland all took the first step in the exit procedure by issuing an Environmental Failure Notice on October 6, 2008. Despite the notice, and in violation of the export credit contracts, construction of the dam continued regardless. Therefore on 23rd December 2008, all three governments suspended their export credit guarantees.

International demonstrations

Even following suspension of the export credit guarantees, contractors continued to push ahead with removing villagers from the project affected area in a way that violated the 153 conditions. The Ilisu dam project was a subject of widespread resistance both within and outside Turkey. Thousands of people demonstrated in Hasaneyf, the ancient town that the Ilisu dam would destroy. Activists blocked the Brandenburg gate in Berlin and the headquarters of the Austrian ECA. A worldwide petition to stop Ilisu dam and preserve the region as a UNESCO world heritage site attracted thousands of signatures.

On July 7, 2009, the German, Austrian and Swiss governments officially ended the export credit guarantee contracts for the Ilisu dam, because ‘the requirements tied to this insurance cover in the areas of the environment, cultural heritage and resettlement could not be fulfilled…’’

More information

Visit the Stop Ilisu dam campaign page.

 

Publications archive

Find more publications related to Atradius in the publications section.